| Construction cost excl. VAT | Building activity fee |
|---|---|
| € 10 000 | € 285 |
| € 25 000 | € 712 |
| € 50 000 | € 1 422 |
| € 100 000 | € 2 770 |
| € 250 000 | € 6 280 |
| € 500 000 | € 10 636 |
indien de bouwkosten: a. minder bedragen dan € 500,-- : € 45,95 b. € 500,-- of meer bedragen, doch minder dan € 2.500,--: per € 500,--, aan bouwkosten € 17,25 met een minimum van € 59,30 c. € 2.500,-- of meer bedragen, doch minder dan € 50.000,--: per € 500,--, bouwkosten € 14,25 met een minimumSource: Legesverordening 2026, Tarieventabel artikel 2.5. read on 2026-10-13. Reliability: verified on the source.
If your plan also needs a check against the environment plan, a separate fee usually applies. The municipality sets the final amount in its decision; this page is not a decision of the municipality.
Describe your job in plain words. AstraNL structures the request and looks for an executor. There is no confirmed tradesperson or price for you yet.
Ask for help